City Makes Progress on Processing Building Permits

The City of Corner brook has been making real progress in processing building permits and we have the statistics to show it.

We have been working with our staff over the past 4 years to ensure that you get fewer delays and faster turn around times on your permit applications. when you provide all the information required, our professional staff can process most applications relatively quickly – in fact so far this year 92% of all applications are delivered within 5 days.

Building Permits

August 2017

Permit Percentages August # of permits (Aug) Year to Date % Total # of Permits
% of Permits Issued the Same Day 44% 31 40% 145
% of Permits 3 days or less 85% 60 88% 320
% of permits 5 days or less 89% 63 92% 337
% of permits 6 to 10 days 3% 2 2% 6
% of permits more than 10 days 8% 6 6% 21
Totals 71 364

 

 